The Foundation update | November

Blog

October 2025 – The Foundation

The story so far…

Here’s an overview of the journey we’ve been on so far with The Foundation.

In 2023 we started fundraising, with a view to ‘Make the Most’ of the building that was part of our site at Solihull.

We put the contract out to tender in Autumn 2024 as planned. However, the exploratory work highlighted some issues with the existing building including the stability of the ground beneath the floor (stronger in some parts of the building) as well as significant cost increases (total building projected to cost £3.4m). This has led us to make some changes to The Foundation project:

​​Change the design – rather than spending significant money on ground works, we have ‘flipped’ the design around so that areas needing stronger foundations are at the end of the building with the best ground conditions. Here is what has changed from the original design:

– Some parts of the original design removed, such as the link to the Community Hub and the mezzanine floor, as this was adding significant cost.

– Design specifications changed to find cost effective alternatives but without impacting on quality.

– New tender process to allow us to obtain competitive quotes for different aspects of the build, rather than allow a single company to control all of the costs.

April 2025 we updated the church with these plans and the current cost assumptions.

The current cost stood at £2.49m – and we were hoping to reduce this further through our tender process. Throughout April and May we had contractors on site. They were focussing on the drainage work, clearing the building and floor surveys. This was preparatory work as we got ready for awarding the main contracts for the building work to start fully later in 2025.

May 2025 – The first phase of remedial works started.

June 2025 – Asbestos removed, final surveys neared completion and we carried out the final preparatory work.

August 2025 – Bible Burial – watch the video here.

September 2025

-Concrete poured – we continued to make good progress on the build!

– Expected total cost of has reduced further, cost reduction is from four main areas – design, value engineering, procurement and VAT saving.

We are now aiming for The Foundation open in April 2026 – complete with a foyer, performance space, studio and multi-use sports area. Current cost estimated at £1.9m – an incredible saving from original estimates of £3.4m in 2024.

We are so excited as a church for what is to come – and to see The Foundation used to support our mission as we continue to go ‘From One. To Many.’ as we grow our space and capacity to impact our groups, young people within and outside of Renewal and our local community, helping them to encounter Jesus whilst making the most of our amazing new space!

If you’d like to support The Foundation financially, find out ways to give here.

Sign up for the newsletter

Pop your details in here if you want to hear what is happening in the life of Renewal every week!

"(Required)" indicates required fields

Submit